Project: League of
California Cities- LEED CI Gold
Complete
renovation of existing four-story building, 8-month duration. MTA developed the schedule and move plan for the
League of California Cities and their five tenants to relocate to temporary
locations prior to allow construction to occur unimpeded. MTA collaborated with architect and contractor early
in the project to design electrical circuitry required for furniture and
equipment. MTA dimensioned out
electrical and data locations in the field for all private offices and open plan
locations and field verified of all power/data/mechanical locations as well as
critical dimensions during key points in construction. A short-term lease at
the temporary facility carried a costly penalty if not vacated on time.
MTA worked closely with contractor
to install furniture in phases during construction to allow adequate time frame
for LEED required off-gassing period, without delaying move in past the lease
expiration date. MTA also
developed the schedule and move plan to relocate the LOCC and their tenants into
their new spaces at their newly renovated facility.